Worked example
A 5 m x 4 m roof slab, 150 mm thick, in M20
Inputs
- Slab 5 m x 4 m x 0.15 m = 3.0 m³
- M20 nominal mix 1 : 1.5 : 3, water-cement ratio 0.5
- 5% wastage, so 3.15 m³ of wet concrete
Working
- Dry volume = 3.15 x 1.54 = 4.85 m³, split over 5.5 parts
- Cement = 4.85 / 5.5 x 1440 kg/m³ = 1270 kg = 25.4 bags
- Sand = 1.32 m³; aggregate = 2.65 m³; water = 1270 x 0.5 = 635 L
Result: About 26 bags of cement, 1.3 m³ of sand (47 ft³) and 2.7 m³ of 20 mm aggregate (94 ft³).